The Ramsar Secretariat Work Plan 2007
as adopted by the 35th meeting of the Standing Committee
Secretariat Work Plan 2007: Key tasks and indicators
Note. The staff time allocation is based on each staff full-time equivalent (FTE) working 46 weeks in the year, using a base figure of 18 FTE staff. This figure takes into account staff who work for less than full-time, and staff posts whose recruitment is anticipated part way through 2007. Interns are counted as FTE staff.
|
Task |
Staff weeks 2007 |
Indicators |
|
Organise and hold Standing Committee 35, Feb 2007 |
29.2 |
SC35 held |
|
Organise and hold STRP mid-term workshops, March 2007 |
23.1 |
Workshops held; work plan progress facilitated |
|
Develop and maintain an electronic system for communication amongst STRP members & with its National Focal Points |
6.4 |
STRP NFPs assisted to have improved involvement in STRP’s work |
|
Support STRP in its elaboration and delivery of priority tasks in its Work Plan |
37.0 |
Immediate & High Priority STRP tasks progressed according to Work Plan |
|
Work with IOPs to ensure a common framework for assistance in delivering the Convention’s implementation |
9.1 |
Framework and collaborative activities agreed |
|
Develop a new approach to improving the financial base for the Convention’s implementation |
7.3 |
SC36 has a new format for budget framework |
|
Arrange occasional briefings of Missions in Geneva on activities taking place between Standing Committee meetings |
9.1 |
At least one briefing held |
|
Provide briefings to Standing Committee members between SC meetings, as required during the year |
9.0 |
At least two briefings (July & October) sent to SC |
|
Implement the CEPA Programme, and further develop a comprehensive plan for CEPA internally, including the activities undertaken with Danone Group and other private sector actors, through CEPA Oversight Panel |
44.4 |
Comprehensive Secretariat CEPA plan, with input of CEPA Oversight Panel, developed |
|
Publish Ramsar Wise Use Handbooks and Ramsar Technical Reports |
22.4 |
Publication of 3rd edition Handbooks completed; RTRs published in a timely manner |
|
Maintain Ramsar Web site, listserves and other electronic information provision |
14.4 |
Topical information on the Convention available to all stakeholders |
|
Seek to enhance the development of capacity building through the Advisory Board on Capacity Building for the Ramsar Convention and developing regional centres |
8.8 |
Advisory Board contributing to capacity-building for Parties |
|
Prepare materials and advice for WWD 2008 (and follow up on 2007) |
27.7 |
WWD 2008 materials prepared and despatched; 2007 activities reported on Web site |
|
Agree and begin to implement, with the Convention on Biological Diversity, a 4th Joint Work Plan 2007-2009 |
6.0 |
4th JWP being implemented |
|
Use proactively the Biodiversity Liaison Group, and the Joint Liaison Group for the Rio Conventions, to improve synergies |
4.3 |
BLG meetings attended, JLG meetings attended as observer, both at SG/DSG level |
|
Promote the work of the Convention at important international meetings |
25.3 |
SRA level or above represented Convention at key global and regional meetings |
|
Prepare paper for CSD on Ramsar and water in 2008 |
2.0 |
Paper prepared & distributed |
|
With the SC Subgroup, begin preparation of the Strategic Plan for 2009-2014 |
6.0 |
First Draft Strategic Plan circulated to SC during 2007 |
|
With the SC Subgroup and interested Parties, develop and issue a new National Report Format for COP10 |
7.6 |
COP10 National Report Format issued in 2007 |
|
With the Management Working Group (MWG), review the existing management structures of the Secretariat and Convention |
2.4 |
Any changes to management structures advised by MWG implemented by Secretariat |
|
Further develop the review of COP decisions called for in Resolution IX.17, as instructed by SC35 |
2.5 |
Recommendations resulting from the review prepared for SC36 consideration |
|
With the Host Government and other relevant bodies and agencies, continue to develop options for the change of status of the Secretariat (Resolution IX.10) |
3.4 |
Further advice on options prepared for SC36 and potential COP10 consideration |
|
Manage the core funding support for, and monitor the implementation of, regional initiatives approved by Resolution IX.7 |
15.9 |
Approved funds transferred to regional initiatives; advice on implementation progress & issues provided to SC |
|
Undertake project evaluations and reviews (SGF, WFF, SFA, etc.) |
55.6 |
All project proposals and reports evaluated |
|
Monitor implementation of COP9 Resolutions |
13.8 |
Implementation progress by Parties and IOPs tracked, as required |
|
With the Republic of Korea, implement the Memorandum of Understanding for COP10 |
11.0 |
COP10 planning documents prepared; Republic of Korea advised on COP preparations |
|
Support organization of COP10 regional preparatory meetings by host countries |
27.9 |
All regional meetings prepared or held |
|
Continue to review the effectiveness of Memoranda of Understanding with other organisations |
3.6 |
All Memoranda and annexed plans either updated, replaced or annulled |
|
Advise countries in the process of accession on any issues of clarification, and on preparing their first RIS, as necessary |
16.5 |
Kazakhstan, Lao PDR, UAE, Yemen and others further assisted for accession |
|
Assist Parties with implementation of the Convention |
74.1 |
Advice and support on national implementation issues provided, in regional and global contexts |
|
Manage and process Ramsar site designations and RIS updates |
108.2 |
All RISs received from Parties fully processed |
|
Advise Parties on Article 3.2, Montreux Record and Ramsar Advisory Mission (RAM) issues |
13.3 |
Article 3.2 issues raised with relevant Parties; RAMs prepared when requested by Parties |
|
Undertake general administration of the Secretariat and Convention |
146.9 |
Parties, and other stakeholders, provided with a timely and efficient service |
|
Make representations to Parties in arrears with contributions |
4.9 |
Meetings with missions made |
|
Organise SC36 and COP10 Subgroup meetings |
17.0 |
|
|
Organise Secretariat meetings with partners and other stakeholders, as needed |
11.0 |
Meetings prepared in timely manner |
For
further information about the Ramsar Convention on Wetlands, please contact
the Ramsar Convention Secretariat, Rue Mauverney 28, CH-1196
Gland, Switzerland (tel +41 22 999 0170, fax +41 22 999 0169, e-mail
).
Posted 19 February 2007, Dwight Peck, Ramsar.